What it is
A schedule of works lists the work to be done, usually room by room or trade by trade, with enough description for a contractor to price it and for the client to check what is included.
What it should contain
Strip-out, structural works, services, plastering, joinery, finishes and external works, with references to the drawings and specification. Items supplied by the client, such as sanitaryware or appliances, should be identified so that only fitting is priced.
Provisional sums
Where something cannot be known until work starts, such as the condition of joists or the extent of damp, a provisional sum is included and adjusted against the actual work. Clear provisional sums are better than hidden assumptions.
Using it on site
The schedule becomes the basis for valuations, payments and changes. When something is added or omitted, it is recorded against the schedule, which keeps the final account straightforward.
Common questions
Who writes the schedule of works?
An architect, surveyor or the contractor, depending on how the project is procured. For an insurance claim it is usually prepared by the contractor and agreed with the loss adjuster.
Is a schedule needed for a small job?
Even a short written list makes a quote clearer and avoids misunderstandings about what is included.